Project Details

Project Type: Other

View map of project area

Metro Project #: 14-SC-0153

Council District(s):

Sewer basin: Central

Designer: Brown and Caldwell, Hazen and Sawyer

Contractor:

Contact Us

Project Timeline

Phase Start Finish
Design September 2015 February 2018
Permitting/Bid/Award February 2018 September 2018
Construction September 2018 January 2022