Ewing Creek - Brick Church Equalization Facility

This project consists of the construction of a 10.6 million gallon pre-stressed concrete tank and an 18 millon gallons per day pump station. The storage tank is utilized when sewer flows exceed the capacity of the existing sewer system. The peak flows are stored until the flows in the system recede, and the stored volume can be conveyed through the system to treatment. Without the construction of this facility, flows in excess of the system capacity resulted in sanitary sewer overflows.

Project Details

Project Type: Equalization Facility

View map of project area

Metro Project #: 11-SC-0110

Council District(s): 3

Sewer basin: Whites Creek

Designer: GRW Engineers, Inc.

Contractor: Cumberland Valley Constructors, Inc.

Contact Us

Project Timeline

Phase Start Finish
Design August 2015 December 2016
Permitting/Bid/Award December 2016 May 2017
Construction May 2017 October 2018