Berwick Trail Pump Station Upgrades

To convey additional flows and address nearby sanitary sewer overflows, this project includes the construction of a new pump station with greater capacity. Approximately 7,100 linear feet of the associated force main will be upgraded as part of the Neely’s Bend Pump Station Upgrades project to convey the additional flow from the increased capacities of the Berwick Trail Pump Station and Neely’s Bend Pump Station.

Project Details

Project Type: Pump Station

View map of project area

Metro Project #: 11-SC-0107

Council District(s): 9

Sewer basin: Dry Creek

Designer:

Contractor:

Contact Us

Project Timeline

Phase Start Finish
Design March 2020 November 2021
Permitting/Bid/Award November 2021 May 2022
Construction May 2022 June 2023