28th Avenue Rehabilitation – Area 2 – Batavia Street

This project was developed to renew aging infrastructure and address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 47,300 linear feet of gravity sewer, associated manholes, and service laterals within Metro’s right-of-way and easements.

Project Details

Project Type: Rehabilitation

View map of project area

Metro Project #: 11-SC-135B

Council District(s): 21,24

Sewer basin: Central

Designer:

Contractor:

Contact Us

Project Timeline

Phase Start Finish
Design November 2019 May 2020
Permitting/Bid/Award May 2020 May 2021
Construction May 2021 July 2022