Annual Rehabilitation FY2016 - South Hurricane Creek

Completed February 2018

Evaluation and rehabilitation of approximately 53,400 linear feet of sewer, manholes, and laterals within Metro’s rights-of-way and easements with the goals of reducing rainfall-derived infiltration and inflow (RDII) and renewing existing infrastructure for the southern Hurricane Creek sewer basin.

Project Details

Project Type: Rehabilitation
Project Area Map: View map
Metro Project #: 16-SC-0009
Council District(s): 33
Sewer basin: All
Designer: Hethcoat & Davis, Inc
Contractor: Insituform Technologies, LLC

Project Timeline

Phase Start Finish
Design March 2016 December 2016
Permitting/Bid/Award December 2016 May 2017
Construction May 2017 March 2019

Project Photos